Circle/Properties/OXO The Residences
Current Stage
Gate 4 of 8 — Architecture, Doors & Windows
Structure is complete. Currently installing doors, windows, and architectural elements. Interior finishing, pools, and landscaping to follow. Expected handover: 31 October 2026.
Construction
52%
On Schedule
Yes
Handover
31 Oct 2026
Next Milestone
Interior Finishing
Land AcquisitionOperations
Milestones Completed
✓
Gate 1: Land Acquisition & Due DiligenceJun 2025
1,200 sqm site in Canggu secured. Legal review and notarial deed complete.
✓
Gate 2: Permits & ApprovalsAug 2025
IMB building permit, environmental clearance, site plan approved by regency.
✓
Gate 3: Foundation & StructureFeb 2026
Reinforced concrete foundation and steel structure for all 6 residences erected.
4
Gate 4: Architecture, Doors & WindowsIn Progress
Roofing complete. Currently installing aluminum doors, windows, and facade elements.
5
Gate 5: Interior FinishingMay 2026
Flooring, bathrooms, kitchens, electrical, plumbing, tiling.
6
Gate 6: Pool & LandscapingJul 2026
6 private pools, tropical garden, irrigation, outdoor areas.
7
Gate 7: Furnishing & StylingSep 2026
Custom furniture, art, linens, kitchenware, smart home integration.
What's Happening Now
•
Doors & Windows Installation
Aluminum framing and glass installation in progress across Residences 1-4.
•
Structure Signed Off
Structural engineer inspection passed. All load-bearing elements approved.
•
Facade Work Started
Natural stone facade cladding began on Residence 1 this week.
•
Interior Design Finalized
Material selections approved for all 6 units. Tiling procurement underway.
•
On Track for Oct Handover
Currently 3 days ahead of schedule. No weather delays this quarter.
Coming Up
10 AprWindow installation complete — all units
18 AprOXO Circle investor event — site visit
01 MayInterior finishing begins — flooring & tiling
15 JunBathroom & kitchen fit-out
01 JulPool excavation begins
31 OctTarget handover date
Latest Updates
Structure Complete — Moving to Facade & Openings26 Mar 2026
All 6 residences have completed structural work. Roofing done. Now installing doors, windows, and stone facade.
Made SutrisnaInterior Design Selections Finalized15 Mar 2026
Material palette approved: Italian porcelain tiles, teak cabinetry, terrazzo bathrooms. Procurement begins next week.
Johannes WieseConstruction Progress Report — February 202601 Mar 2026
Roofing installed on Residences 4-6. Waterproofing complete. Electrical rough-in started.
Johannes WieseSite Visit Photos — Structural Milestone10 Feb 2026
Photo documentation of the structural completion milestone. All concrete and steel work signed off by engineer.
Made Sutrisna1–4 of 4
1 / 1